Client appointed JSM to deliver a new fibre infrastructure network for their client. Due to the complexity of the project, it has been agreed to deliver it in 2 phases.
£multimillion
5 Months
May 2023
JSM has been appointed by a well established Telecoms provider to deliver a whole infrastructure network in Essex.
Delivery and Approach
Phase 1 comprised a whole range of activities including new civils build, BT Openreach PIA installation in duct and overhead, new cabinets and customer connection (Toby) boxes.
Specifically, Phase 1 included the delivery of:
29,645m Cabling in total to enable future connection of up to 2021 residences.
JSM adapted to exacting client’s demanding reporting criteria, including daily reporting to the client to monitor progress and programme. JSM also raised the PIA orders on the BTOR portal on behalf of the client, taking responsibility for the initial route order, network adjustments, whereabouts of closing out of the PIA orders. JSM has brought benefit and efficiencies to the client by recording the whole build on GPS to assist with closing the build sections down quickly.
Challenges and Solutions