FROM CONCEPT
TO CONNECTION
snap shot
Value: Six figures
Distance: 32km
Duration: 3 months
Hollow Core Fibre Connection – Data Centre
The client required 32km of hollow core fibre (HCF) to be installed between Central and West London.
THE CHALLENGES
Communication and authorisation from the Canal & River Trust (CRT) for canal works presented a key challenge, requiring coordination and compliance with strict regulatory requirements.
WHAT WE DELIVERED
- JSM planned and managed all phases of this multi-million pound project, including feasibility studies, permitting, and installation.
- Special Engineering Difficulties (SEDs), including works crossing canals were managed in compliance with key stakeholders.
- In addition to the 32km of HCF, 16 new chambers were constructed.
32KM
HCF
16
chambers
46m
new ductwork
specialisms used
- As-builts drawings
- 46 new Ductwork
- Hollow Core Fibre
- Splicing
- Fibre installation
“There were a lot of moving parts on this project, especially working along canal routes and coordinating access. Keeping close communication with all parties made a big difference in delivering everything efficiently.“
Toby Ford
Head of Operations