FROM CONCEPT
TO CONNECTION
snap shot
Value: Multi Million
Voltage: 33kV
Duration: 10 months
21MVA Battery Energy Storage System
The client required the design, construction, and commissioning of a 21MVA Battery Energy Storage System (BESS) compound in Broadditch, Kent.
THE CHALLENGES
Site earthing presented a challenge due to the 33kV overhead line connection and the planned future 11kV connection, requiring careful consideration of combined fault contributions and differing clearance times. In addition, site constraints made plant installation difficult, as the six 32-ton batteries required a complex lifting operation into position.
WHAT WE DELIVERED
- 6nr batteries
- 3nr transformers
- 460m of 33kV cabling,
- 2-panel 33kV switchboard,
6nr
Batteries
460m
OF 33kV CABLING
3nr
TRANSFORMERS
specialisms used
- Compound construction
- Compound earthing
- DNO switchgear & substation
- Battery Installation
- Duct installation
- LVAC supplies
- Jointing & Terminations
- Hot and cold commissioning
with Energisation
“From the outset, the project relied on careful design integration and coordination on site to manage constraints and ensure safe installation. That approach was key to achieving a robust and compliant end result.“
Martyn Crocker
Operations Director