FROM CONCEPT

icon

TO CONNECTION

snap shot
Value: Multi Million
Voltage: 33kV
Duration: 8 months

33kV Solar Farm Connection

The client required the design, installation, and commissioning of a 15MVA 33kV DNO switchroom and cable route in Basildon, Essex.

THE CHALLENGES

The cable route needed to cross the busy A127 into London, creating congestion and logistical constraints. At the same time, a nearby third-party project planned to excavate along the same route, increasing coordination complexity and the risk of disruption to local residents.

WHAT WE DELIVERED

  • JSM provided detailed design and approvals, supply and installation of the switchroom with battery chargers and metering room, and 4.2km of 33kV cable ducting with cable pulling and jointing
  • Horizontal Directional Drilling (HDD) was used to cross under a busy road
  • Collaboration with an adjacent 3rd party project sharing the same route avoided multiple excavations on a busy road

15

MVA

4.2km

CABLE DUCTING

33kV

DNO

SWITCHROOM

specialisms used

  • Principal designer
  • Principal contractor
  • Compound construction
  • Compound earthing
  • 4.2km cable route
  • 33kV Cables & Duct installation
  • LVAC supplies
  • Jointing & Terminations
  • Hot and cold commissioning
    with Energisation
Delivering this scheme required a joined-up approach from design through to energisation, with a strong focus on coordination throughout. By working closely with stakeholders and planning around key constraints, we were able to keep disruption down while maintaining a smooth and efficient delivery.
Martyn Crocker
Operations Director