FROM CONCEPT

icon

TO CONNECTION

snap shot
Value: Multi Million
Voltage: 132kV
Duration: 18 months

132kV DATA CENTRE CONNECTION

The client required the design and build of a 70MVA 132kV Data Centre connection in Hemel Hempstead, Hertfordshire.

THE CHALLENGES

Complex construction is required, including HDD beneath the M25 under strict National Highways constraints, installing plants and ducts across the River Colne, and safely routing ducts over petrol pipelines and high-pressure gas mains.

WHAT WE DELIVERED

  • JSM constructed a 132/33kV DNO and customer substation and a 16km 132kV dual circuit in highly congested roads
  • The Special Engineering Difficulties (SEDs) included crossing the M25. Horizontal Directional Drilling (HDD) was employed to ensure no disruption to traffic
  • Horizontal Directional Drilling (HDD) was also used to cross a river whilst meeting all environmental standards

16km

132kV Dual circuit 

30

132kV Joint bays

60

Fibre chambers

specialisms used

  • Auxiliary transformer design
  • Compound construction
  • Compound earthing
  • Motorway monitoring
  • Horizontal directional drilling
  • Jointing & Terminations
  • Hot and cold commissioning
    with Energisation
This project demonstrates our ability to deliver large-scale, high-voltage infrastructure in highly constrained environments. By combining technical expertise with a collaborative approach, we’re able to provide solutions that support the growing demand for data centre capacity.
James Cooper
Head of Business Development

FROM CONCEPT

icon

TO CONNECTION

snap shot
Value: Multi Million
Voltage: 132kV
Duration: 21 days

SPECIAL ENGINEERING DIFFICULTY

A cable crossing over the River Colne and Colne Brook was required to connect a Data Centre to Iver Substation.

THE CHALLENGES

Limited engineering options make it challenging to meet infrastructure needs while also protecting the environment.

WHAT WE DELIVERED

  • Bridge-mounted and Horizontal Directional Drilling (HDD) methods were ruled out, leaving open-cut excavation as the only option
  • Works were completed in 21 days following two years of planning and ecological safeguards

Dam

Installation

Designs

Permits and Ecological surveys

specialisms used

  • Cable Crossing
  • Open cut excavation
  • Dewatering
This project required a careful balance between delivering essential infrastructure and protecting a highly sensitive river environment. With challenges around working in a live watercourse, managing dewatering, and protecting local wildlife, detailed planning and close monitoring on site were critical to minimising impact and maintaining full compliance.
Claire Parsons
Environmental Manager

FROM CONCEPT

icon

TO CONNECTION

snap shot
Value: Multi Million
Diameter: 160mm to 89mm ducts
Duration: 25 months

132kV Energy to Waste Connection

The client required the design, installation, and commissioning of a new 132kV electrical supply system to support energy recovery operations in Belvedere, Dartford.

THE CHALLENGES

The tidal location of the river created a significant flood risk and required careful environmental planning. Complex signal structures on constrained bridge crossings introduced additional engineering and approval challenges, while the proximity to a dual carriageway demanded strict traffic management. The site’s ecological sensitivity, including nesting birds and protected wildlife, limited construction activities, alongside the need to account for structural load and thermal expansion. The exposed installation also presented risks of vandalism and unauthorised access.

WHAT WE DELIVERED

  • Special Engineering Difficulties (SED) included constrained bridge crossings requiring Horizontal Directional Drilling (HDD) beneath roads
  • Potential for flooding due to the river’s tidal nature necessitated placing the pipe bridge above the bridge soffit and within the protection of the Thames Estuary flood defences. Polytetrafluoroethylene (PTFE) sliding bearings and expansion joints were used to accommodate thermal and structural movement without compromising flood resilience

10.6km

cable route

132kV

Electrical supply system

160mm to 89mm

Ducts

 

 

specialisms used

  • Installation
  • Commissioning of high-voltage
  • Bridge crossings
  • HDD (Horizontal Directional Drilling)
  • Diamond coring
This project brought together complex engineering and environmental considerations in a highly constrained location. Through detailed planning and close coordination, we were able to deliver a compliant and resilient 132kV connection while minimising disruption and ensuring long-term reliability.
Macc Flynn
Client Project lead

FROM CONCEPT

icon

TO CONNECTION

snap shot
Value: Multi Million
Voltage: 132kV
Duration: 36 months

132kV Data Centre Connection

The client required the delivery of a 6.5km civil infrastructure route, primarily within public highways, as part of a 60MVA 132kV Data Centre connection in Hemel Hempstead, Hertfordshire.

THE CHALLENGES

Construction couldn’t be completed in one phase due to early commissioning requirements, so works were staggered and required complex sequencing from temporary to permanent systems. The project involved specialist 132kV equipment and precise coordination with existing infrastructure, alongside significant site constraints including water ingress, depth limits, pipeline crossings, and a congested industrial route.

WHAT WE DELIVERED

  • JSM constructed a dedicated 11kV substation, a 132kV dual transformer bund area, and an iDNO-adoptable 132kV switchgear compound
  • Temporary power was required during substation works, resulting in 1.6km of 11kV cables being installed. This prevented delays to the client’s energisation requirements
  • The Special Engineering Difficulties included bypassing a bridge. Horizontal Directional Drilling (HDD) was used to ensure no disruption to traffic

6.5km

CIVIL INFRASTRUCTURE ROUTE

132kV

DATA CENTRE CONNECTION

60

MVA

specialisms used

  • Principal Designer
  • Principal Contractor
  • Project management
  • Cables and Duct installation
  • HV/EHV Plant installation
  • Comissioning
  • On Load testing/Energisation
Delivering this project required exceptional coordination and adaptability from our team. From phased construction and complex sequencing to navigating challenging ground conditions and critical infrastructure crossings, we worked closely with all stakeholders to safely deliver a resilient, high-capacity connection within demanding time constraints.
Martyn Crocker
Operations Director