FROM CONCEPT
TO CONNECTION
snap shot
Value: Multi Million
Distance: 130km
Duration: 10 months
130km Fibre Installation
The client required a new network build spanning 130km along a route from Welwyn to Slough that included canal and bridge crossings.
THE CHALLENGES
Complex multi-borough delivery with challenging third‑party access and dependencies, combined with a long, constrained route. Additional difficulties included engineering constraints and limited access points such as canal towpaths.
WHAT WE DELIVERED
- JSM planned and managed the multi-million pound project, including stakeholder engagement, surveys, redesign, construction, Horizontal Directional Drilling (HDD), ducting, fibre installation and testing.
- The team installed 130km of fibre with 64 joints.
- Over 100 Special Engineering Difficulties (SEDs) were managed, including the use of barges and pontoons to manage access and carry out works safely.
130km route
WELWYN TO SLOUGH
64
JOINTS
100
SEDs MANAGED
specialisms used
- Surveys and route proving
- Duct roping
- Chamber build
- Duct supply and Installation
- 432f Fibre Installation
- Splicing and testing
- Project management
- Permits and notices
- Traffic management